The Homewood retention pond project, which began under former Mayor-President Josh Guillory’s administration, will be completed by the end of next year, according to Lafayette Mayor-President Monique Boulet.
Boulet’s administration secured $22 million in state reimbursements that were held up due to changes to the project under Guillory that didn’t go through the joint budget approval process, State Rep. Troy Hebert said at a Friday press conference.
The next step for the Homewood project, located in the Milton area, is removing deactivated gas pipelines that run through the property, which will begin in December and be completed by February, Lafayette Consolidated Government’s Chief Administrative Officer Rachel Godeaux said during the press conference.
Removal of the pipelines was estimated to cost around $6 million. Gulf South, the pipeline owner, worked with the administration to donate the pipelines to LCG, reducing the removal cost to $250,000, Boulet noted.
Following that, the administration plans to start connecting the Homewood ponds to the Vermilion River, a segment expected to take around eight months to complete, according to Godeaux.
The project is part of the larger Bayou Vermilion Flood Control project, which aims to relieve flooding along the Vermilion River during rain events. Another part of the project that had stalled under Guillory, Coulee Ile Des Cannes, was completed in September.
The Homewood project launched in 2022 under Guillory and was suspended in November 2023 due to the lack of funding from the Louisiana Facility Planning and Control Program. When Boulet took office, she was tasked with remedying improper and incomplete permitting, contractor issues and uncertainties around state reimbursement.
In 2024, LCG received $6.1 million in reimbursement, but the remaining $22 million wouldn’t be secured until the 2026 legislative session.
Another $8 million in funding is earmarked to connect the ponds to the river, Boulet said. So far, LGG has spent more than $100 million on the proposed $60 million project.
After the connection is made, the administration has to figure out what to do with the additional 300 acres of land on the property. That land was purchased with federal American Rescue Plan Act dollars and was promised for a specific use. Any deviation from that would require the administration to seek fed approval.
One thing the administration made clear on Friday is that it will not be made into a park, at least not anytime soon. Godeaux said the administration lacks the necessary funding to construct a new park in the parish.
Another question is what to do with the millions of cubic yards of dirt that were created when constructing the ponds. The administration said it was in negotiations with companies to remove the dirt from the property.